This will help you in understanding steps to Link and De-link estimates from PO’s
Note: Linking and Delinking of estimate can be done if the PO is in New or Rejected state
Step 1: Open Marketing Purchase Order app
Step 2: Go to ATL POs
Step 3: Click on Action Button
Step 4: Click on Delink Estimate option
Step 5: User will receive a success notification after delinking of the estimate
Step 6: User can link the estimates by clicking on Link estimate option available in actions
Step 7: Select one estimate and click on “Link”
Step 8: Review the PO details and click on 'Save PO' button to update the new estimate details to the existing PO