How to Link and De-link estimates from PO’s?

Created by Ria Gomes, Modified on Fri, 1 Jul, 2022 at 8:34 PM by Pankaj Amesar

This will help you in understanding steps to Link and De-link estimates from PO’s


Note: Linking and Delinking of estimate can be done if the PO is in New or Rejected state

Step 1: Open Marketing Purchase Order app
Step 2: Go to ATL POs
Step 3: Click on Action Button





Step 4: Click on Delink Estimate option

Step 5: User will receive a success notification after delinking of the estimate



Step 6: User can link the estimates by clicking on Link estimate option available in actions



Step 7: Select one estimate and click on “Link”



Step 8: Review the PO details and click on 'Save PO' button to update the new estimate details to the existing PO



Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article